|
Case Studies: Landslides in Hong Kong |
2. Managing Slope Safety |
The following two articles provide an overview of
the landslip problem in Hong Kong and measures taken by government
to reduce the risk from landslip hazard. Both articles were
written by Dr A.W. Malone, an Honorary Associate Professor in the
Department of Earth Sciences, University of Hong Kong and former
Director of the Hong Kong Geotechnical Engineering Office.
1
Slope Safety Systems for Asian Cities
by Dr Andrew Malone
Abstract
A methodology based on systems concepts and risk management
principles is presented here for the design of slope safety management
systems for cities where rain-induced landsliding is a serious social
problem. A model action plan is suggested as a guide to setting
up such a safety system and the associated costs are given.
keywords: landslides, safety management, system design
Introduction
Many cities in Asia have experienced strong economic
and population growth in recent decades, including a number in tropical
and sub-tropical Asia with adverse terrain and climate. Some city
governments have been forced into permitting the exploitation of
hillslope land to provide housing and roads but the control regimes
needed to ensure a good quality built environment, well protected
against intense rainstorms, have not been put in place. Such polices
leave a legacy of unsafe cut slopes, loose fill embankments on sloping
ground and substandard retaining structures. Rain-induced landsliding
is becoming a serious social problem in a number of these cities
because of multi-fatality building collapses caused by landslide
impact and a growing landslide death toll on the roads. How are
city governments to respond? How are limited resources best invested
in slope safety?
One of the first cities in the region to face these problems was
Hong Kong, which began to tackle the issue in the 1970s. A well-developed
safety regime is now in place (I]. Hong Kong's comprehensive slope
safety regime is taken as a model by other growing cities in the
region with an adverse climate and terrain where rain-induced landsliding
is commonplace. In Hong Kong new slope works are tightly controlled,
old slopes are being brought up to modern safety standards under
a long-term works programme, routine slope maintenance is encouraged,
hillside shantytowns are being progressively cleared and rainstorm
emergency preparedness measures are in place. The regime is supported
by a strong research effort and its effectiveness is monitored systematically.
The slope safety regime in Hong Kong appears to be the product of
a comprehensive design. But it is not the creation of a grand plan,
rather it is the result of step-wise evolution over a thirty-year
period. Each step, every new element of the regime, came about as
a reaction to one or more multi-fatality landslides that had aroused
strong public concern [2]. Hong Kong's case is not unusual in this
regard - looking at safety regimes in other disaster scenarios we
find that crisis-driven evolution is the norm. However, as we shall
see later, safety regimes which develop reactively have severe disadvantages
and, until the time eventually comes when the whole is in place,
do not meet the needs of the parties involved. If needs are to be
met, a system must be designed to meet needs. But
how is such a design to be carried out?
Research has shown that a slope safety system designed on risk management
principles, centrally coordinated by a safety manager and with effective
public communication by the authorities responsible will largely
meet the needs of the community. The finding is likely to be generally
valid and so this paper has been written as a guide to establishing
such a safety system, for the benefit of interested parties in cities
with slope safety problems. Before proceeding, the concepts used
in the paper will be introduced and terms defined.
Concepts
System |
comprises elements functioning together
to achieve an objective; not a randomly assembled set of elements
system outputs must be measured and compared with the desired
output and adjustments
made so that the future output will be close to that desired
|
System Objective |
to meet the needs of the parties
e.g. the Resource Allocator needs proof that investment to reduce
risk has achieve the intended outcome |
System Parties
(stakeholders) |
the public (the risk bearers)
property owners (the risk creators)
the Safety Manager (system design and management)
the Regulator (safety control of new works, etc.)
the Resource Allocator (the provider of legitimacy, information
and monetary and physical resources to the Safety manager and
Regulator)
the media, etc. |
System Actions |
by property owners (physical works,
warnings, etc.)
by the public (precautionary action, etc.)
interactions between the parties (economic, information, policing,
etc.) |
Slope Safety Programmes |
new development control, existing
slopes (retrofitting & maintenance, squatter clearance)
emergency preparedness, research and development, public communication,
system monitoring and improvement |
Risk |
chance of defined harm |
Risk Criteria |
nationally set criteria defining
the level of 'unacceptable risk' and 'broadly acceptable risk';
the 'ALARP' region lies between these limits |
Risk Management |
the process of risk analysis, evaluation
and control: estimate risk and if 'unacceptable', reduce at
all costs; if risk is in the ALARP region, reduce to As Low
As Reasonably Practicable (ALARP) |
Public Communication Rationale |
responsible parties must win trust,
promote accurate understanding and maintain awareness; must
not give unwarranted reassurance, which is liable to backfire
|
Retrofit works |
works needed to bring an old structure
up to modem safety standards |
Elaboration of the Design Concepts
Let us treat Hong Kong's slope safety regime as a
'system', as defined above. We can recognise the 'parties' involved
in the system, their actions and interactions, and we can see the
overall system operating plan as expressed in the Slope Safety Programmes.
The system has an explicit objective, the reduction of landslide
risk, expressed quantitatively [3], and the broader mission of the
Safety Manager (the Geotechnical Engineering Office) is to meet
the needs of the community. The outcomes of the system are monitored
and a feedback mechanism is in place to make the improvements to
the system shown to be needed by outcome monitoring. Whilst the
end product meets the needs of the community, the evolutionary process
by which the complete system was assembled has a number of undesirable
features and in this regard Hong Kong's experience serves as a warning
to others. The undesirable characteristics of crisis-driven evolution
are summarised in Table 1.
Table 1. Features of crisis-driven evolution
- shock and panic after disaster
- blame seeking and scapegoat
- money 'thrown at' the problem and its effectiveness overstated
- only one class of defect rectified after each disaster
- premature public reassurance and no emergency preparedness
- risk rises as people forget
|
The alternative to crisis-driven evolution which avoids
these undesirable features is to commission a complete system from
the outset. The design must be fit for purpose but what should be
the design objective? The objective most likely to gain acceptance
is 'to meet the needs of the parties'. What do we mean by 'needs'?
By way of illustration let us consider some of the needs of one
of the parties, the 'Resource Allocator', and examine the efficacy
of a system design methodology based on the application of the principles
of risk management. The approach we will adopt follows risk management
methodology as applied in many countries to the management of major
technological hazards by the public regulator [4].
Two acute questions facing the Resource Allocator will be 'how much
resources should be allocated to slope safety?' and 'how can we
prove to the investor (eg the taxpayer) that the investment has
been resource effective?', Economic evaluation of a proposed slope
safety project, following normal prudent commercial principles,
would require that benefits exceed costs by an ample margin. But
this rationale is unlikely to release sufficient resources to the
project to satisfy public expectation. So then how much 'subsidy'
is justifiable? Risk management policy as applied in the regulation
of technological hazard provides the rationale to answer the question.
If, say for a nuclear power station, estimated risk is 'unacceptably'
high, when compared to national risk criteria, the hazard regulator
will require that it should be reduced at all cost. However when
risk is within the ALARP region (defined in the national risk criteria),
the regulator will only require that it should be reduced to As
Low As Reasonably Practicable, When applied by hazard regulators
the ALARP requirement translates into a condition that investment
in risk reduction should proceed to the point at which incremental
'trouble, time and expense' becomes grossly disproportionate to
incremental benefit. If the risk management methodology is adopted,
the Resource Allocator can work out the answer to the first question.
The Resource Allocator will have a defensible allocation rationale.
The second question concerns performance measures. If the outcome
of the slope safety project is monitored in terms of risk reduction
achieved and the costs and benefits are quantified, the Resource
Allocator has the evidence needed to measure resource effectiveness,
a valid performance measure for the project.
This briefly illustrates the application of the methodology in the
case of one party, but the needs of other parties are also to some
degree served through the employment of the risk management rationale.
But the risk management rationale alone is not a sufficient basis
for system design. An effective public communication policy is also
required, Risk creators (eg property owners), the Safety Manager
and the Resource Allocator all need to engage in effective dialogue
with the risk bearers. A public communication rationale has to be
established with the aim of winning trust, promoting understanding
and maintaining awareness. Experience shows that all of the parties
communicate with each other mainly via the electronic and print
media. So the media are a vitally important party in the safety
management system.
Plan of Action
Let us assume that a decision has been taken to set
up a slope safety system. How is the city government to proceed?
A model plan of action is given in Table 2. The design process,
given in Table 3, starts with a scoping study and preparation of
an outline system design.
Table 2. Sequence of Actions
1. |
appoint Safety Manager
|
Year-1 |
2. |
start Research Unit |
|
3. |
make policy submission
and preliminary resource bid |
|
4. |
carry out system design
(Table 3) |
|
5. |
make detailed resource
bid |
|
6. |
receive mandate |
|
7. |
commence emergency preparedness
actions and public education programme |
Year-2 |
8. |
begin squatter relocation
|
|
9. |
start data acquisition
and annual reviews of system |
|
10. |
enhance control of new
slope works |
|
11. |
provide public information
service on hazards |
|
12. |
start remedial works and
retrofit |
|
This provides detail for the policy submission and
preliminary resource bid to the Resource Allocator, timed on the
annual budgetary cycle. With these applications in the pipeline
the main design effort begins. This requires compilation of historical
landslide and rainfall data-bases, so that historical landslide
occurrence frequencies and detriment trend can be established. Development
of a hazard model follows, along with frequency and consequence
assessments for the global quantified risk analysis (QRA)[5]. The
QRA should determine present risk and past risk trend.
Table 3. System Design Process
1. |
scoping study & outline
design |
2. |
data-bases & risk
models |
3. |
needs analysis |
4. |
QRA & CBA |
5. |
prepare risk reduction
packages |
The 'needs analysis' is an essential part of system design (item
3, Table 3). Its purpose is to elicit the needs of the parties
through opinion survey and later to check the degree to which
each of the risk reduction packages potentially meets needs. Then
follows the quantification of the costs and benefits (cost/benefit
analysis CBA) of the various risk reduction packages which the
System Manager will offer as options to the Resource Allocator.
Each package consist of several measures, some to reduce frequency
of occurrence of landslides and others to cut exposure of people
to harm and property to damage. Each of the packages will be justified
using the ALARP rationale in quantified form (invest until incremental
cost becomes grossly disproportionate to incremental benefit)
or qualitatively ('do your best') for the non-quantifiable elements.
Each package includes a mechanism for measuring system outcome
and resource cost per unit of outcome ('effectiveness'), a device
for providing feedback to improve future outcomes and a public
communications plan. The Resource Allocator will in due course
decide what is 'reasonably practicable' and make public the reasoning.
A package of risk reduction measures might include some emergency
preparedness actions, a public education campaign, enhancements
of control of slope works, certain funding for old slope retrofit,
etc. put together as an initial say 5-year plan. The measures,
along with the associated research, monitoring and public communications
actions would be implemented through long-term Slope Safety Programmes
(Section 1).
Once detailed design is completed the Safety Manager is able to
make a detailed and fully justified application to the Resource
Allocator. The programme given in Table 2 assumes this application
is made in Year-1 month-9 and that there is a 3-month period between
the date of this application and receipt of mandate for whatever
risk reduction package is chosen by the Resource Allocator. Major
capital funding approvals and legislative amendments will take
longer than three months, but the associated start dates for remedial/retrofit
works and regulatory upgrading are phased in the second half of
Year-2. Having completed system design, the Research Unit shifts
emphasis to procurement (Table 4) and preparatory technical work
for Year-2.
The second year sees the beginning of intervention, starting with
potentially the most resource effective/quick acting measures
such as emergency preparedness actions and public education campaigns.
Before the public launching of the emergency preparedness programme,
preparatory work will be needed with the media if they are to
help the Safety Manager to train up the other parties. The new
data acquisition systems for rainfall, landslides, slope inventories
and social survey will come into operation in Year-2, so that
by the end of that year the first annual review can be carried
out. Once this data is available it should be put on the Internet
for open access. This will save community costs and aid consumer
choice. In the second half of Year-2 a start will be made to upgrade
the control regime for new development, including town planning
and building control.
Later in Year-2 the Regulator will start to administer the voluntary
or mandatory programme of remedial and retrofit works to old slopes
by property owners, governmental and private. The retrofit programme
should be very carefully planned as it will prove to be the most
expensive component of the system, as we shall now see.
Costs
Table 4. Costs of a Slope Safety Management System
Party |
Staffing |
Procurements |
Safety Manager |
manager + 2 GE |
landslide investigation consultancy
(US$1.2m per year) |
Research Unit |
head + 4 GE |
geotechnical/risk consultancy
for databases, data acquisition system, QRA/CBA, risk zonation
plans, etc (US$0.5m per year)
weather radar (US$1.2m) automatic raingauges (US$0.2m + US$3000
per gauge per year)
public education campaign, social survey, media training &
public relations consultancy (US$0.2m per year)
or checking (review) consultancy (US$20,000 per permit) |
Regulator |
head + 2 GE technical secretariat
+ 1 GE per 30 permits per year
(GE also handles slope repair notices, landslide inspection,
etc.) |
|
Notes:
1. 1 GE = a geotechnical engineer + share of divisional
technical & clerical staff (basic salary cost US$0.15m
per GE) + share of departmental expenses, not rent (US$30,000
per GE).
2. Annual costs at 1997 prices in Hong Kong, where human
resource costs are very high.
3. Number of GEs needed depends on number of registered
hazardous features, availability of technical support elsewhere
in the organisation, etc. Number given is the minimum. |
An indicative cost estimate for a notional Slope Safety System
is given in Table 4. It should be noted that these rates
applied in Hong Kong in 1997. Appropriate adjustments will be
needed for other Asian cities. What are the relative costs
of this notional system compared to retrofitting? The cost of
retrofit works to a typical 60' cut slope in saprolite 50m long
x 15m high might be HK$2.5m (1997 prices). These include soil
nailing, raking drains and surface protection and drainage. The
annual cost of the entire safety system given in Table 4 (assuming
weather radar amortised over 10 years, 20 raingauges, 150 permits
per year, manager and heads cost 2xGE, GE on cost factor 2.0)
is about the same as the cost of only 30 retrofits. The annual
cost of the slope works control function only is equal to 10 retrofits.
The cost of ten retrofits, out of the thousands likely to be needed,
is surely a small annual price to pay for ensuring that slope
works in 150 new projects per year are of an adequate quality.
But this logic alone, based as it is on the avoidance of future
loss, is unlikely to convince hard-pressed city authorities to
invest in slope controls. However, once the landslide problem
has become a social issue, city managers might be attracted by
the possibility of preventing of all of the social and political
problems that would certainly accompany future disasters, some
of which are given in Table 1. In this regard it is helpful to
examine the history of slope control in the two cities which are
perhaps the most advanced in this area: Rio de Janeiro and Hong
Kong.
When was effective regulation of hillside development
introduced in Hong Kong and Rio de Janeiro?
The two cities have much in common: similar population, land
areas, adverse terrain and climate. Both cities experienced rapid
economic growth, immigration and building boom in the second half
of the twentieth century, resulting in land shortage and the growth
of squatter communities comprising patrial immigrants living at
risk in shantytowns on steep hillsides. Early hillslope development
was permitted without effective safety controls. In both places
a succession of multi-fatality landslides occurred, provoking
public outcry. The authorities subsequently brought in effective
slope safety regulation (Table 5). Both cities were relatively
poor at the time compared to cities in the developed countries,
but slope regulation had become imperative politically.
Table 5. Regulation in relation to Disaster
|
Regulation
Introduced |
Prior
Landslide
Fatalities |
Population
at the time |
GDP
per capita
at the time
|
Rio de Janeiro |
1966 |
73 (1962&
1966) |
3.8m |
? (US$ 6000
in 1997) |
Hong Kong |
1977 |
175 (1972 &
1976) |
4.5m |
US$ 1600
(US$ 25,000 in 1997) |
When should effective control of new slope works
be introduced?
In these two cases timely pre-emptive action would have avoided
much loss of life and social crisis. But how do the authorities
know when to take such action? In deciding, it may be helpful
to examine detriment trends and this can be done quite cheaply.
If a graph of landslide fatalities in Hong Kong per year versus
time had been drawn up in 1966, after the disastrous June rainstorm,
a disturbing trend would have emerged (see Figure 1, Malone 1997
[1]). Landslide fatality figures for squatters had been rising
with population growth since the 1940s and by the 1960s landslide
fatalities were just starting to occur post-war on roads and in
buildings. Reason perhaps to consider corrective action?
Had a good slope safety system been introduced in 1966 in Hong
Kong, 200 lives may not have been lost subsequently due to landslides
and Hong Kong's slope retrofit bill may have been reduced by 25%
or more. But Hong Kong is now relatively wealthy and the government,
much the biggest landowner, is apparently able to afford the level
of investment in slope retrofit expected of it by the community.
In contrast, other cities with similar adverse climate, terrain
and population pressures may, in time, find that they are unable
to afford to pay for the retrofit needed to drive risk down a
level which the community is prepared to tolerate. Not only is
risk rising apace in times of economic boom with unregulated development,
but tolerance levels are failing with increased political liberty,
universal education, widespread wealth and a free press [6]. The
logical answer to the headline question is the sooner the better
and well before the essential retrofit bill becomes unaffordable.
Conclusions
A design methodology and action plan has been given to help interested
parties to establish a slope safety system, designed on risk management
principles, which meets the needs of the community. When should
such a system be introduced? It is prudent economically and politically
wise for governments to introduce these systems before their essential
slope retrofit bill becomes unaffordable and before being forced
to do so in the wake of repeated disaster.
References
1. Malone, A.W. (1997). Risk Management and Slope Safety in
Hong Kong. Transactions of the Hong Kong Institution of Engineers,
4, No.2, pp 12-21.
2. Malone, A.W. & K.K.S. Ho (1995). Learning from landslip
disasters in Hong Kong. Built Environment, 21, Nos. 2/3,
pp. 126-144.
3. Government of the Hong Kong Special Administrative Region
of the Peoples Republic of China (1998). Policy Address by
the Chief Executive: Slope Safety for All, Policy Objective
for Works Bureau. HKSAR Government.
4. Health and Safety Executive (1988). The tolerability
of risk from nuclear power stations. London: HMSO.
5. Wong, H. N. & K.K.S.Ho (1998). Overview of risk of
old man-made slopes and retaining walls in Hong Kong. Slope
Engineering in Hong Kong, Balkema, pp. 193-200.
6. Bond, M.H. (1991). Beyond the Chinese face: Insights
from psychology, Hong Kong, Oxford University Press.
|
|